The State Road (SR) 710 PD&E Study began in January 2008 and is anticipated to be completed by the end of 2013. The project activities include data collection, development of roadway improvement alternatives and evaluation of potential social and environmental effects. The potential corridors for the proposed extension of SR 710 from US 441 to SR 70 were presented at a Corridor Public Information Workshop on October 22, 2009. The alternative roadway alignments were presented at an alternatives public workshop on April 5, 2010. We held a public hearing on January 30, 2013.

On March 16, 2017, the Florida Department of Transportation (FDOT) Office of Environmental Management (OEM) granted Location and Design Concept Acceptance for the SR 710 PD&E Study. This project is now eligible to move to the next phase of development.

Click schedule to see larger graphic.Schedule Graphic 03/2017